Klozur® (sodium persulfate) and PermeOx® Plus Used to Remediate Groundwater at Former Oil Refinery Pipeline Release

ORIN successfully remediated the site by injecting Klozur® (sodium persulfate) and PermeOx® Plus chemistry through a series of direct push points over a five-day period.

Products
Contaminants Treated

Benzene

Type of Site

Pipeline Release

Consultant

ORIN

SITUATIONAL SUMMARY

4,700 ppb of benzene was present in the groundwater at the 60,000 ft.3 site. Treatment application consisted of chemical injection through a series of direct push points of Klozur® (Sodium Persulfate) followed by PermeOx® Plus over a five-day period. 

RESULTS

Benzene concentrations were reduced from 4,700 ug/l to 3.3 ug/l. Down-gradient wells outside the active injection area also showed a significant reduction.